Mediclinic City Hospital is one of the main structures located in the Dubai Healthcare City (DHCC) that was launched in 2002 by His Highness Sheikh Mohammed Bin Rashid Al Maktoum to meet the demand for high-quality patient centred healthcare.
Swissboring has been appointed as main contractor in the enabling works and piles foundations as well as dewatering and excavation for the expansion of the North Wing of existing Mediclinic City hospital.
Owner | Mediclinic City hospital |
Consultant | Hyder |
Main Contractor | Swissboring |
Qty | 4000 m² of retaining wall and 220 bored piles |
Size |
700 mm of thickness for retaining wall, ø 700 to 900 mm for bored piles with average lenght of 30 m |